MGNREGA
Annual target of the Scheme (Man-days) 898111

Cumulative man-days provided at the end of the previous month 381613

Number of man-days provided in the current month 180401

Jal Jeevan Mission
Annual target of the Scheme 65

Cumulative Physical Progress at the end of the previous month 40

Physical progress in the current month 8

National Health Mission
Annual target of the Scheme 0

Cumulative expenditure incurred at the end of the previous month 0

Expenditure incurred in the current month 0

Number of Projects undertaken in the month 0

Soil Health Card
Deen Dayal Upadhyay Yojna
Amount of loan disbursed in the current month 0

Cumulative amount of loan disbursed till the end of the previous month 0

Number of beneficiaries covered in current month 0

Number of beneficiaries targeted in the year 10

Total number of beneficiaries covered till the end of the previous month 0

CM Arogya Arunachal Yojna
Annual target of the Scheme 0

Cumulative Physical Progress at the end of the previous month 13901

Physical progress in the current month 58

Swachh Bharat Mission (Urban)- Collection/ Disposal of garbage/ Solid Waste
Average kms run of garbage collection vehicles 19440

Number of garbage collection vehicles pressed into service monthly 7

Number of manpower engaged for garbage collection 12

Total number of village households 3974

Total quantity/ amount of garbage collected and processed during the month 246

Blue Revolution
Annual Target 0

Cumulative Physical Progress at the end of the previous month 0

Physical progress in the current month 0

Rashtirya Krishi Vikas Yojna
Annual Target 54

Cumulative Physical Progress at the end of the previous month 54

Physical progress in the current month 0